The Brief
Tapper Interiors were appointed as a sub-contractor to provide interior fit out and exterior cladding works for the Deck 92 area at Land Rover Solihull.
What We Did
New facility including front office, amenities and Reception.
Construction within Jaguar Land Rover live operations in 2 Phases
Tapper Interiors Installed
- External plasterboard ceilings to reception area entrance
- Double skin steel partitions
- External Wall lining and internal partitions
- Plasterboard and grid/tile suspended ceilings
- XL composite glazed screens incorporating integral remote controlled blinds
- Internal doorsets and joinery
- Raised access flooring
- Hygienic wall cladding in WC areas
- IPS Panelling system
How We Made a Difference
The work was completed on time and to a very high standard. As a result of this, the next phase of work to form a VIP Walkway and Visitors Centre was successfully negotiated
Main Contractor:
Anglo Holt Construction Ltd
Value:
£276,000
Scope:
- Client Walkway
- Elliptical Building Interior
- Fit Out
- Bespoke Curved Doors
- East Works Visitors Centre
Duration:
16 Weeks
Completed:
June 2012
Sector:
Motor Industry
Gallery
“If your aim as a business is to deliver a quality product to the client then you can have confidence that Tapper Interiors will deliver. The Deck 92 and Visitors Centre was a quality product”
Andrew Hall, Director, Anglo Holt Construction Ltd